The short answer
A BRUKL report is the standard compliance output produced by approved non-domestic energy-modelling software. It records the calculated performance of the proposed or completed building against the applicable Part L targets.
SBEM is one approved route used to create the energy model. The BRUKL report presents the compliance results and the supporting specification; it is not a separate design calculation and it is not a substitute for the information entered into the model.
What the report shows
The report records the target and building primary energy rates, the target and building emission rates and the specification used in the calculation. It also provides checks against the relevant minimum standards and other information generated by the approved software.
A passing result depends on the complete model rather than one product or system. Geometry, activities, fabric, glazing, air permeability, lighting, HVAC efficiencies, controls and renewable technologies can all influence the outcome.
Design-stage and as-built BRUKL reports
The design-stage report is produced before construction from the proposed drawings and specification. It gives building control a record of the assessed design and helps the project team identify a compliance risk before work is fixed on site.
The as-built report must describe the building as completed. Installed products, systems, commissioning information, air-test results and changes from the design-stage specification should be reflected in the final model. The applicable Approved Document also sets signature requirements for the final report.
What to send the assessor
Provide coordinated plans, sections and elevations, an area schedule and clear room uses. The model also requires construction build-ups, window and door performance, air-permeability information, lighting data, heating, cooling, ventilation and hot-water details, controls and any renewable-energy proposal.
Confirm the jurisdiction, Building Regulations route and project dates before relying on a methodology or software version. Transitional arrangements can affect the correct assessment route, so a live project should be checked rather than assumed from the publication date alone.
Official sources
Published 24 March 2026 · Last updated 8 September 2026